Date
|
Activity
|
Notes
|
| Feb 11 |
Loft 1
|
Began lofting, will continue next week |
| Feb 18 |
Loft 1 |
Finished lofting |
| Mar 3 |
Station molds |
Made Station Molds |
| Mar 10 |
Patterns: stem, transom knee, transom/ mill stem, knee, and transom/ glue up stem and transom |
Milled and glued up stem and transom. |
| Mar 31 |
Shape stem and transom. Rabbet stem, mill keel. |
Shaped stem and transom. Erected Station molds. |
| Apr 7 |
Set up ladder frame, erect molds/ rough out transom |
Mill keel & keelson and set backbone |
| Apr 14 |
Set up transom, backbone, and stem |
Rabbet stem. Mill and fit deadwood. Mill lining off battens. Start lining off planking. |
| Apr 21 |
Line off planking, start planking patterns |
|
| May 5 |
Garboards |
|
| May 26 |
Broadstrakes |
|
| Jun 9 |
Strake 3 |
|
| Jun 23 |
Strake 4 |
|
| Jun 30 |
Strake 5 |
|
| Jul 7 |
Strake 6 |
|
| Jul 21 |
Strake 7 |
|
| Aug 4 |
Sheerstrakes |
|
| Aug 11 |
Patterns for quarter knees, breasthook, mill, glue up/ mill frames, fit quarterknees |
|
| Aug 18 |
First coat interior; shape breasthook, install |
|
| Sept 1 |
Sand interior, frame out |
|
|
Mill, fit bilge runners, fit brass half-oval on stem, keel, bilge runners |
|
|
Mill, fasten guards, fasten knees, breasthook |
|
|
Fit inwales, rivet, trim frame heads |
|
|
Mill and fit risers, thwarts |
|
|
Mill and fit sternsheets, bow seat, backrest |
|
|
Pattern, mill, fit thwart knees forward and aft |
|
|
Mill, fit, mortise oarlock pads |
|
|
Pattern, mill, fit floorboards |
|
|
Prime interior coat 2 |
|
|
Sand interior, enamel coat 1 |
|
|
Sand interior, enamel coat 2 |
|
|
Prime exterior coat 1 |
|
|
Sand exterior, prime coat 2 |
|
|
Sand exterior, enamel coat 1 |
|
|
Sand exterior, enamel coat 2 |
|
|
Sand/paint contrasting sheerstrake |
|
|
Install keel band, splice painter |
|
|
|
|
|
|
|
|
|
|
|
|
|